Progress report on NE Corridor Infrastructure projects

Nov 8, 2018 | Light Rail, Transportation

The city of Charlotte on Oct. 23 released this update on seven projects underway along the Blue Line Extension to improve connectivity between stations and nearby communities, whether traveling on foot, on bike or in a motor vehicle. The projects and several others comprise the Northeast Corridor Infrastructure Improvement Program. Total cost of the projects will exceed $106 million when completed in the next few years.

 

J.W. Clay Boulevard streetscape

Map of J.W. Clay Boulevard streetscape plan.

Map of J.W. Clay Boulevard streetscape plan.

Design is 90 percent complete, and real estate acquisition is expected to start in late 2018. During the real estate phase, the City acquires the property rights needed to build and maintain the improvements that were identified during the design phase.

City real estate agents will reach out to affected property owners with information on the City’s real estate acquisition process. Construction is expected to be complete by the end of 2021. Project website

 

Rocky River Road West streetscape

Real estate acquisition is almost complete and the site is being prepared for utility relocation. This will involve moving fences and clearing trees for utilities to make way for new poles, guy wires and overhead lines. Construction is expected to start in the fall of 2019. Project website

 

25th Street connection

This project is now in the utility relocation phase, during which utility infrastructure such as underground gas, water and sewer lines, as well as overhead power, telephone and television lines are moved as needed to make way for construction.

By the end of the year, the City will invite contractors to submit bids to construct the project. Construction is expected to start by mid-2019. Project website

 

Parkwood Avenue streetscape

Design continues on this project, which is expected to be complete in late 2018, after which real estate acquisition will begin.

During the real estate phase, the City acquires the property rights needed to build and maintain the improvements that were identified during the design phase.

City real estate agents will reach out to affected property owners with information on the City’s real estate acquisition process. Project website

 

North Tryon and 36th Street streetscape

Design is 90 percent complete, and real estate acquisition is expected to start in late 2018. During the real estate phase, the City acquires the property rights needed to build and maintain the improvements that were identified during the design phase.

City real estate agents will reach out to affected property owners with information on the City’s real estate acquisition process. Project website

 

Tom Hunter Road streetscape

Plan for Tom Hunter Road

Streetscape plan for Tom Hunter Road

Design is almost complete, and real estate acquisition is about to begin. During the real estate phase, the City acquires the property rights needed to build and maintain the improvements that were identified during the design phase.

City real estate agents will reach out to affected property owners with information on the City’s real estate acquisition process.

The project team will host an open house in late 2018 to share the design with the public.

Residents will receive a postcard containing meeting information once they are determined, and subscribers will be notified. Project website

 

Orr Road Extension

This project will start the bidding process in October 2018. During the bid phase, the City, through a competitive bidding process, procures the services of contractors as needed to build the project.

By state law, the lowest responsible bidder is awarded the construction contract. Construction is expected to start in early to mid-2019. Project website

0 Comments


Receive Up to Date News


Receive Economic Development News


View Past Newsletters


View Post by Category


Press Releases

Meet Jordan Harris

This month, UCP welcomed Jordan Harris as the Director of Community Development and Outreach. With over a decade of community relations experience in various roles, most recently serving as the associate director of community relations at UNC Charlotte. In her new...

We’re Back…with a Vision!

University City Vision Plan – Connecting: People. Places. Nature. The growth and development being realized in University City is nothing short of transformational.  Major investments in transportation and mobility infrastructure, thousands of new rooftops, new...

University City launches Barton Creek Greenway Native Meadow

By Azania Herron University City Partners, University of North Carolina at Charlotte Botanical Gardens and North Carolina Native Plant Society have partnered to install Barton Creek Greenway Native Meadows, a community native plant project in University City. On April...

New Farmers Market to open Oct. 3 at University Place

University City Partners announces the opening of University City Farmers Market on Oct. 3 around the lake at The Shoppes at University Place. Shoppers will find fresh local produce, food preparation programs and live entertainment. Open every Saturday in October The...

University City Wine Fest to Offer Socially Distanced Activities

New This Year: Wine on the Water and a Boutique Dining Experience.  Greystar University City Wine Fest will return this fall at multiple locations around the lake and boardwalk at Shoppes at University Place. The fourth annual festival will take place from September...

Where Will They Play?

We need more parks now – YOU CAN HELP A crisis caused by Charlotte’s explosive growth and government inaction threatens one of the most important assets of every truly livable city – public parks.   A recent nationwide study revealed that Charlotte has the least...